Nitish Setu: Why Bihar's newest 6-lane Ganga bridge took 14 years—and how it will transform travel to Patna
Bihar's six-lane Ganga river bridge connecting Kachchi Dargah in Patna to Bidupur in Vaishali—named Nitish Setu—has been completed after roughly 14 years, with Prime Minister Narendra Modi set to dedicate the 19.76-km project to the nation on November 21, 2026.
Bihar's six-lane Ganga river bridge connecting Kachchi Dargah in Patna to Bidupur in Vaishali—named Nitish Setu—has been completed after roughly 14 years, with Prime Minister Narendra Modi set to dedicate the 19.76-km project to the nation on November 21, 2026.
The six-lane Ganga bridge in Bihar, which connects Bidupur in Vaishali and Kachchi Dargah in Patna, has become a reality after almost 14 years. Prime Minister Narendra Modi inaugurated the project, also called Nitish Setu, on November 21. The project encompasses 19.76 km of length, including the main bridge over the river Ganga, which is about 9.76 km in length. The bridge will boost the road network of Bihar, thereby helping connect Patna with North Bihar.
The Ganga bridge will relieve Gandhi Setu of the traffic it has been facing for years. The bridge, once opened, will ease traffic on Gandhi Setu, thus helping the people who have to come to Patna from Vaishali, Hajipur, and neighbouring towns.
The opening of the bridge is also expected to bring year-round connectivity to residents of Raghopur Diara and adjoining areas, which otherwise witness double crossing seasons every year.
14 years of planning and execution of the Ganga bridge
The journey towards completion has taken more than 10 years of planning, arranging finance, and construction.
2012-2013: The Chief Minister of Bihar, Nitish Kumar, gave the initial approval for the project in September 2012. The project consultants started working in 2013 when they made the feasibility report of the project. The final presentation was made in front of Nitish Kumar in June 2013, who was shown the complete plan.
2014-2015: The Union Government approved the project in December 2014, thus enabling the negotiations with the Asian Development Bank (ADB) for getting the ADB loan, followed by the administrative approval from the Bihar government in the year 2015.
January 16, 2017: The International tendering process completed and the construction work commenced on January 16, 2017.
November 21, 2026: Prime Minister Narendra Modi shall give away the completed six-lane bridge to the general populace.
There is a direct financial outlay approved under the project of about ₹4,988.40 crore comprising the contribution of the Government of Bihar and the help from ADB.
The bridge passing through Samrat Chaudhary's name based on Nitish Kumar's contributions
Chief Minister Samrat Chaudhary announced that the bridge would be named Nitish Setu to recognise former Chief Minister Nitish Kumar's role in expanding Bihar's road infrastructure. The decision drew pushback from the opposition, with Tejashwi Yadav questioning the naming choice and demanding the bridge be named after freedom fighter Akshwat Rai.